Estimated Project Costs and Schedule | Plans + Projects | Our Work

Estimated Project Costs and Schedule

Cost

Eastbound, peak-period vehicle lane $36 million
Bicycle/pedestrian path and related improvements $24 million
Planning, environmental review, design

$14 million

Construction management and Caltrans oversight

$14 million

TOTAL $88 million

Schedule

Environmental approval (Completed) August 2016
Final design/construction permit (Completed) August 2016
Construction begins (Completed) January 2017
Third eastbound traffic lane project completion (Completed) April 2018
Bicycle/pedestrian path project completion (Completed) November 2019
Project Complete August 2020