I-880 Alameda County

I-880 between Oakland and Milpitas

MTC plans to convert the existing I-880 HOV lanes that run from Hegenberger Road to Dixon Landing Road in the southbound direction and from Dixon Landing Road to Lewelling Blvd. in the northbound direction to an express lane. The conversion involves lane striping and installing sign gantries, signs, FasTrak® toll tag readers, traffic monitoring video cameras and CHP observation areas. It will result in 51 express lane miles from Oakland to Milpitas. This express lane project is coordinated with Caltrans and will follow the progression of Caltrans’ project to replace the median barrier on I-880.

Work on the project started in the south in September 2017 and will move north up the corridor, with the entire project expected to last two and half years. To sign up to receive I-880 Express Lane construction notices, email info@bayareaexpresslanes.org.