Independent Experts Recommend Interim Bay Bridge Fix

Committee to Announce Opening Date at Thursday Meeting

UPDATE:

August 15, 2013 — The state Toll Bridge Program Oversight Committee (TBPOC) today gave a green light to an interim fix to the seismic system on the new Bay Bridge East Span, and determined that the new East Span will open to traffic by 5 a.m. on Tuesday, September 3, 2013, following a five-day bridge closure that will begin the evening of Wednesday, August 28. Visit BayBridgeInfo.org for updates on the closure.

OAKLAND, CA The state Toll Bridge Program Oversight Committee (TBPOC) today announced that it has received a report from the Federal Highway Administration in which the federal agency concludes that installing temporary seismic elements will make the new East Span of the San Francisco-Oakland Bay Bridge safe for traffic, and should be put in place as quickly as possible. This plan involves inserting large steel plates, known as shims, into each of four bearings, enhancing their ability to safely distribute energy during an earthquake.

The TBPOC in July asked federal highway officials to analyze the shim installation plan to assess its viability to allow the new East Span to open prior to the permanent retrofit for broken bolts on the easternmost pier of the self-anchored suspension portion of the new bridge. Federal officials recommend adopting that plan. This recommendation is consistent with that of internationally known bridge designers Dr. Peter Taylor of Buckland & Taylor, Ltd., in North Vancouver, B.C., and Dr. John Kulicki of Modjeski and Masters in Mechanicsburg, Pa., who submitted separate analyses of the shimming strategy originally advocated by the Toll Bridge Seismic Safety Peer Review Panel. Each of these independent reports can be viewed online at mtc.ca.gov and at baybridgeinfo.org.

“Safety has always been the driving factor for any decision related to this lifeline bridge, and these reports confirm that the temporary fix could allow us to safely move traffic while work continues on a permanent retrofit,” said Steve Heminger, Chairman of the TBPOC. “We will meet in a public session to discuss this important information and to announce the opening date for the Bay Bridge.”

At the July meeting, the TBPOC concluded its investigation into the breakage of a batch of large bolts on the eastern span of the Bay Bridge and recommended that the bridge opening be postponed from the previously announced opening on Labor Day, 2013, until further engineering work could be completed and considered.

The Toll Bridge Oversight Committee will hold a public meeting on Thursday, Aug. 15, at 10 a.m. at the MetroCenter Auditorium, 101 Eighth Street, Oakland, at which time these reports will be discussed and the opening date for the new East Span will be announced. The meeting will be audiocast at mtc.ca.gov/meetings/schedule.

The Toll Bridge Program Oversight Committee was created by the State Legislature in 2005 to provide project oversight and project control for the Toll Bridge Seismic Retrofit Program in California. The TBPOC is comprised of the Director of the Department of Transportation (Caltrans), the Executive Director of the Bay Area Toll Authority (BATA), and the Executive Director of the California Transportation Commission (CTC). The Committee’s oversight and control activities include review and approval of contract bid documents, review and resolution of project issues, evaluation and approval of project change orders and claims, and the issuance of monthly and quarterly program progress reports.