Crews Complete Richmond-San Rafael Joint Replacements
31 of 31 New Upper Deck Joints Now in Place
Work crews this morning completed the final concrete pour of the months-long project to replace 31 expansion joints on the westbound upper deck of the Richmond-San Rafael Bridge. With the completion of the final joint replacement, all plates have been removed from the upper deck roadway. Finishing work, including patching, form removal and the application of rubber sealant, will continue through the month of July. To minimize impact to commute traffic, this work will be performed at night. Motorists can expect lane closures most nights this month from 9 p.m. to 5 a.m.