P-TAP 26 Dates & Milestones

Date Milestone
November 1, 2024 MTC advertises call for projects
November 14, 2024

Webinar regarding Call for Projects

December 6, 2024 Applications due to MTC (by 4 p.m.)
March 21, 2025 MTC notifies grant finalists after Administration Committee approval
April 30, 2025 Local contribution checks due to MTC
April-May, 2025 Projects start
April 1, 2026 Final Report/Draft Certification letter due to jurisdictions
April 30, 2026 Final Report

Staff Contact

Sui Tan
Phone: 415-778-5244